Home    
stoptxdotnowmasthead
FAQ's
Frequently Asked Questions of TXDOT in Public Meetings, June 26 2006
10/06/05 Cottage Grove Neighborhood Group Jim Heacock, Stan Cooper
02/16/06 Constituent Meeting; TxDOT Hdqtrs. Jim Heacock, Dana Cote
04/12/06 Constituent Meeting w/ A. Garcia Pat Henry, Jim Heacock
04/20/06 Culberson Townhall Meeting Delvin Dennis
06/08/06 White Oak Flood Mitigation Pond Public Mtg. Pat Henry, Larry Blackburn, design engineer

QUESTION: What is the status of the next stage of the IH10 expansion, from 610 to Taylor street?

  • 4/20/05: It's in the works; we're going to have continuous feeder lanes all along the way with an overhead section over the railroad. The greatest concentration of work is at Washington.

QUESTION: What is the budget for this project?

  • 10/06/05: we don't have that information
  • 04/12/06: we don't have those numbers right now
  • 04/20/06: $40M

QUESTION: Will there be lane closures on the main lanes during this construction?

  • 04/20/06: There will always be 3 main lanes operating although they will be diverted and rerouted as construction moves through the area

QUESTION: When is the start date for this part of the project?

  • 02/16/06: January 2008; trees to be removed in 2007
  • 04/20/06: Bids for construction will "let" January 2007
  • 04/20/06: 6/8/06: The start of the construction is set for September 2007 and the "let" date is January 2007

QUESTION: How long will the construction take?

  • 04/20/06: It will finish when the first section (outside 610) is finished and that is scheduled for December of 2008

QUESTION: Is the design plan finalized?

  • 02/16/06: It's not final until RFP's are issued; until then, there still is an opportunity to make changes
  • 04/12/06: The design work has been completed
  • 04/20/06: Pretty much
  • 06/8/06: The plans for the elevated lanes over the railroad track are on hold; they're only working on TC Jester eastward

QUESTION: What is the purpose of the continuous feeder lanes?

  • 02/16/06: Address flooding; FHA standard; avoid feeder/main lane adjacency in current configuration between Washington + TC Jester stating that there is presently a dangerous merging condition
  • 04/12/06: same as above but primarily flooding
  • 04/20/06: To address the flooding

QUESTION: What is the intended impact of the White Oak Flood Mitigation Ponds?

  • 06/8/06: The purpose is to mitigate all flooding on IH10 between Washington/Westcott and White Oak and includes the mitigation of flooding after the construction of the elevated feeder lanes between Washington and TC Jester
 
   
 
© Copyright 2006 STOPTXDOTNOW.ORG