TXDOT’s IH-10 TC Jester Construction Project Timeline
July 23, 2006

TxDOT does not publish its project process methodology but it appears to have the following key components in consecutive order:

  1. Planning Specification and Estimate phase (PS&E): approx 1 – 36 months
  2. Presentation of PS&E to Technical Advisory Committee as pre-cursor of 3: approx 1 month
  3. Presentation of PS&E plan for approval by the Transportation Policy Council (TPC) which includes elected officials: two weeks
  4. One meeting to the public, with a legal requirement of one-month notice posted somewhere in the newspaper, and public post-meeting comment period of ten days: 1 month
  5. Plans finalized and printed: 2 months
  6. Contract for Sale Docs (the finalized project plans sent to contractors for their review and bids): 1 month
  7. Let Date (the day the TxDOT opens the contractor bids): 2 months
  8. Award Date (date that TxDOT advises contract winner): 1 month
  9. Construction: 6 – 12 months

Source: Above timeline and process is derived from ad hoc information from TxDOT Houston Construction Division, TxDOT Deputy District Engineer, Houston-Galveston Area Council online documents and other informal sources.

Visit TxDOT's website to search for information about their project process and how it involves the public or contact them:

Gary K. Trietsch, P.E.
District Engineer
Houston District
Texas Department of Transportation
7721 Washington Ave.
Houston, TX 77024
713-802-5000

 
   
 
© Copyright 2006 STOPTXDOTNOW.ORG